Bacton Towers Action (BTA) wrote a letter of complaint to Camden Council in April, citing our concerns about the process of redeveloping the Bacton Towers site since they entered into a private agreement with Mount Anvil in September 2022. Our key concerns were:
- Failure to properly consider the impacts on the community, including new residents of the homes in the Mount Anvil scheme.
- Failure to involve residents and businesses in the selection of the developer or the development concept (specifically the three towers).
- Lack of credibility in the claim to be addressing the housing crisis.
Camden responded to our letter of complaint in May. Their response was not to our satisfaction, and so we responded in June. You can read all the correspondence below.
BTA Letter of Complaint to Camden Council (April 2025)
Camden Council response to BTA’s Letter of Complaint (May 2025)
BTA’s reply to Camden Council’s response to complaint (June 2025)